AutoCAD has a very handy command, COPYTOLAYER, that allows copying entities on one layer to another layer.
Is there a similar capability in IntelliCAD?
Re: COPY to LAYER
#2Do you have found a solution? Because I tell the same question today!dooleybob41 wrote: ↑Wed Jul 25, 2018 3:38 pmAutoCAD has a very handy command, COPYTOLAYER, that allows copying entities on one layer to another layer.
Is there a similar capability in IntelliCAD?
My personal solution is:
- On the layer 1, I select the entities.
- I copy them.
- I move the entities to a layer X in the properties panel.
- then on the layer 1, I past the same entities on the same location.
but Autocad make the same with one function, sniff....
Patrick Depoix
Architecte D.P.L.G. & Historien-chercheur en histoire de l'Architecture
Architecte D.P.L.G. & Historien-chercheur en histoire de l'Architecture
Re: COPY to LAYER
#3Hi,
Please refer to the lisp routine that allows copying entities to the current layer.
If you know AutoLISP, you can modify it as you like.
Download here: https://www.dropbox.com/s/mi5w6is07ehq4 ... R.lsp?dl=0
Please refer to the lisp routine that allows copying entities to the current layer.
If you know AutoLISP, you can modify it as you like.
Download here: https://www.dropbox.com/s/mi5w6is07ehq4 ... R.lsp?dl=0
Re: COPY to LAYER
#4Great thanks QuanNguyen.QuanNguyen wrote: ↑Thu Jan 13, 2022 1:39 amHi,
Please refer to the lisp routine that allows copying entities to the current layer.
If you know AutoLISP, you can modify it as you like.
Download here: https://www.dropbox.com/s/mi5w6is07ehq4 ... R.lsp?dl=0
I made some change to copy speedly on the curent layer only:
Activate the layer you want to be the curent layer and select your objets you want duplicate on this layer.
https://1drv.ms/u/s!Al4yBRY9NHg-jC8D2cj ... o?e=MC919U